Solar Energy Projects

Victoria’s Solar

A summary of solar energy facilities in Victoria that are operational, approved, in process and under construction.

Energy Facilities

Status

Capacity (MW)

Operating 550.2
Approved (not operational) 4657.5
Planning permit application lodged and process underway 861
Under construction 710

Total

6728.7

Operating

Project

Maximum Power (MW)

Operator

Location

Commissioned

Bannerton 88 Foresight Solar Fund 11 km south of Robinvale September 2018
Echuca Solar Project 5 ACEnergy 3 km south of Echuca July 2020
Gannawarra 60 Wirsol & Edify Energy 14 km west of Kerang April 2018
Girgarre Project 5 ACEnergy 3 km south west of Girgarre July 2020
Karadoc 112 BayWa r.e. 26 km south of Mildura December 2018
Mildura 3.2 B Electric 19 km south of Mildura
Numurkah 128 Neoen 3.5 km east of Wunghnu July 2019
Numurkah Apsu 5 Apsu 3 km north west of Numurkah
Robinvale 9.2 Murray River Energy Company 2 km south of Robinvale July 2020
Scato Plus Compost Heliostatic 0.5 Raygen 6 km north east of Newbridge
Stanhope Project 5 ACEnergy 5 km south west of Stanhope July 2020
Swan Hill 19.3 Impact Investment Group 3 km west of Swan Hill July 2018
Wemen 110 Wirsol 30 km south west of Robinvale October 2018

Total

526

Approved (not operational)

Proposal

Maximum Power (MW)

Proponent

Location

Approved

Axedale 180 UPC Renewables 7.5 km north east of Axedale March 2020
Baringhup 75 RED 2 km west of Baringup December 2019
Bendigo 55 BayWa r.e. 8 km east of Bridgewater
Carag Carag 12 Enerpac Australia 7 km west of Stanhope May 2019
Carisbrook 90 IB VOGT GMBH 5 km east of Carisbrook June 2018
Carwarp 100 Canadian Solar Group 30 km south of Mildura
Congupna 68 X-Elio 5 km north east of Congupna
Derby 100 ACEnergy 6 km south east of bridgewater
Fifth Street, Merebin 7.5 Powervault Global 7 km west of Mildura
Frasers 75 South Energy 5 km north of Glengarry September 2020
Gannawarra Stage 2 300 Wirsol & Edify Energy 15 km west of Kerang
Girgarre Solar 85 Enel Green Power Australia 6 km south west of Girgarre May 2018
Girgarre Project 2 5 ACEnergy 1.5 km south of Girgarre
Glenrowan 140 Esco Pacific 2 km south west of Glenrowan February 2019
Goorambat 75 South Energy 2 km south of Goorambat
Goorambat Stewarton (East) 250 Neoen 2 km south of Goorambat
Greentech 2 5 ACEnergy 4.5 km south of Yarroweyah July 2019
Greentech 3 5 ACEnergy 13 km north of Rochester
Greentech 5 5 ACEnergy 12 km east of Shepparton
Greentech 6 5 ACEnergy 3 km north of Tatura
Greentech 8 5 ACEnergy 2 km south west of Raywood August 2020
Horsham 130 Esco Pacific 4 km east of Horsham December 2017
Kennedys Creek 150 South Energy 5 km north east of Benalla November 2020
Kerang Acciona 40 Acciona 2 km south of Kerang August 2017
Kerang CleanGen 1 60 CleanGen 4 km south of Kerang August 2012
Kerang CleanGen 2 60 CleanGen 7 km south of Kerang January 2013
Kerang Greenswitch 50 Greenswitch 5 km south of Kerang January 2013
Laceby 70 Bison Energy 5 km north east of Glenrowan September 2020
Lancaster 80 Esco Pacific 8 km east of Kyabram December 2018
Ledcourt 5 GreentechGreentech 16 km north east of Stawell November 2020
Lemnos 100 Neoen 8 km north east of Shepparton
Macorna 100 KIG Energy 15 km west of Cohuna
Maffra 30 ARP Australian Solar 2 km north east of Maffra July 2018
Mallee 250 Energy Australia 20 km south of Mildura
Moira 3 IB VOGT 90 John Symes 2.5 km south of Wungnhu
Mokoan 30 Lightsource BP 9 km west of Glenrowan
Murra Warra 235 RES 22 km south of Warracknabeal December 2017
Naring 60 Lightsource BP 10 km east of Numurkah February 2019
Nhill 5 Vibe Energy 2.5 km south of Nhill August 2020
Nowingi 250 Lyon Group 45 km south of Mildura January 2017
Numurkah Project 5 ACEnergy 5 km north of Numurkah February 2019
Numurkah Project 2 5 ACEnergy 3 km north of Numurkah April 2019
Ouyen 10 BayWa r.e. 1.5 km north of Ouyen April 2017
Prairie 240 Pacific Hydro 3 km west of Mitiamo January 2019
Raywood 200 South Energy 6 km south if Raywood
Red Cliffs 28 Australian Solar Group 25 km south of Mildura October 2015
SSE 331 Sydney Road 5 Southern Sustainable Electric 4 kmeast of Benalla August 2020
Stanhope 30 Globird 2 km east of Sztanhope March 2020
Stanhope Project 2 5 ACEnergy 5 km south east of Stanhope June 2019
Stanhope Project 3 5 ACEnergy 3 km south of Stanhope
Stanhope Project 4 5 ACEnergy 3 km south of Stanhope
Stanhope Project 5 5 ACEnergy 2.5 km north west of Stanhope
Tallygaroopna 30 X-Elio 2 km east of Tallygaroopna
Tatura East 45 CleanGen 6 km east of Tatura
Tragowel 430 Tragowel Pty Ltd 16 km south of Kerang October 2018
Wangaratta 20 Countyside Solar 5 km east of Wangaratta November 2017
Wodonga 50 Wodonga Solar Power 10 km north east of Chiltern February 2018
Wungnhu Project 5 ACEnergy 1.5 km south of Wungnhu April 2019
Wungnhu Solar 102 X-Elio 1.5 km north west of Wungnhu December 2017

Total

4657.5

Planning Permit Application Lodged and Process Underway

Proposal

Maximum Power (MW)

Proponent

Location

New or Amended Permit

Corop 400 Leeson Group 6 km north west of Rushworth New
Goornong 5 ACEnergy 19 km north east of Bendigo New
Greengold Numurkah 5 Greengold Energy 4 km north east of Numurkah New
GVCE Mooroopna 18 GVCE Mooroopna Solar Pty Ltd 1 km south of Mooroopna New
Inverleigh 19 Inverleigh Wind Farm 6 km south of Inverleigh New
Mokoan 2 30 Lightsource BP 9 km west of Glenrowan New
Morwell 70 ARP Australian Solar Pty Ltd 3.5 km south east of Morwell New
Newstead 10 Renewable Newstead 2.5 km west of Newstead New
Perry Bridge 50 Solis Renewable Energy Pty Ltd 8 km east of Stratford New
Ravenswood 63 FRV Services 12.5 km north east of Maldon New
Toolern Vale 16 Tetris Energy Pty Ltd 5.5 km west of Diggers Rest New
Viewbank 75 FRV Services 4 km east of Stanhope New
Winton North 100 Marble Solar 4 km west of Glenrowan New

Total

861

Under Construction

Project

Maximum Power (MW)

Proponent

Location

Cohuna 34 Leeson Group 8.5 km south of Cohuna
Glenrowan West 130 Overland Sun Farming / Wirtgen Invest 5 km west of Glenrowan
Katamatite Project 5 ACEnergy 3.5 km north of Katamatite
Kiamal 350 Eren Renewable Energy 4 km north of Ouyen
Winton 85 FRV 9 km west of Glenrowan
Yatpool 106 Overland Solar Farming 22 km south of Mildura

Total

710

 

The Department of Environment, Land, Water and Planning has not always tracked the development of solar energy facilities in Victoria. The information above has, in most cases, come from local councils and other sources. While all endeavours are made to ensure the information is complete, accurate and current, it should not be assumed to be 100% correct.